Aker BP experienced one of the most significant phases in the history of its projects in the third quarter of this year, as the installation of offshore platforms in two major Norwegian projects named Yggdrasil and Valhall PWP approaches its final stage.

Installation of Platforms and Completion of Subsea Components

In the Yggdrasil project, the Hugin B and Munin platforms were installed during this quarter, and all main subsea components have been fully placed on site. Currently, the connection and commissioning stages at sea are underway. Additionally, the Valhall PWP platforms, which are part of the Valhall PWP-Fenris project, have also been installed. Both the Yggdrasil and Valhall PWP-Fenris projects are progressing as planned, and their initial production is scheduled to begin next summer.

Production and Future Forecasts

Karl Johnny Hersvik, CEO of Aker BP, stated: "With the installation of the Hugin B, Munin, and Valhall PWP platforms, as well as the completion of the main subsea components in Yggdrasil, we have approached the final stage before commissioning both projects. This process assures us that production will commence next summer."

The Skarv Satellites project in the Norwegian Sea was also brought into operation in late August, nearly a year ahead of the initial schedule. Hersvik said: "The early start of this project demonstrates our operational capabilities and the value of developing new resources through existing infrastructure."

During this quarter, net production averaged 374,000 barrels of oil equivalent per day, which has decreased due to maintenance planning, while net sales volume increased by 5% compared to the previous quarter, reaching 396,000 barrels of oil equivalent per day. Aker BP has maintained its annual production forecast between 380,000 and 400,000 barrels of oil equivalent per day.

Looking beyond current projects, Hersvik noted that the company sees significant opportunities in the Norwegian continental shelf and is strengthening its portfolio of opportunities through exploration and new partnerships. Additionally, by utilizing technology, artificial intelligence, and a more integrated operating model, it aims to unlock more resources and improve its working methods. Aker BP currently manages the Alvheim, Eiga, Skarv, Ula, and Valhall projects and is also a partner in the Johan Sverdrup project.

Aker BP has also recently obtained an operating license for the Kjøttkake project to Gjøa, and after initial production, the management of this project will be transferred to DNO.